This site uses cookies to provide you with a great user experience. By using the site, you accept our use of cookies.

Agreeing the final account at practical completion


Client
Rail specialist
Service
Project Quantity Surveying
Location
United Kingdom
Value
Confidential
Sector
Rail facilities

We supported a rail specialist completing its work for a replacement main contractor after the original contractor entered administration. A rapidly agreed NEC4 Option A subcontract carried forward a complex scope and supply-chain history. We managed the commercial position from the outset, addressing change as the works progressed so that the final account could be agreed at practical completion.

Background

The new arrangement needed to complete the earlier subcontract, but the previous activity schedule did not fully describe the variations already introduced. Some work had started without a corresponding completion budget being agreed, leaving scope and warranty issues to resolve.

The existing supply chain was willing to return, but remobilisation costs and revised rates required agreement before new appointments could be put in place. Those early matters would affect both delivery and the eventual account.

Our approach

We treated the final account as an ongoing part of the project rather than a task to begin after completion. The immediate priority was to understand the work being carried forward, the gaps in the activity schedule and the commercial basis on which the supply chain would finish it.

We supported procurement and the negotiation of the necessary subcontract arrangements, including the effect of remobilisation and changes to rates. This helped connect the delivery requirement with the cost and scope being committed.

During the following six months, more than 60 compensation events were raised. We managed the submission process through the main contractor’s document platform and, where platform problems arose, by email, retaining a route for progressing the account within the contractual administration.

The main-contractor account and supply-chain accounts were managed together. Payment applications, assessments, variations and other contractual matters needed to reflect the same developing scope, so that a change upstream did not disappear into an unexplained cost movement downstream.

Monthly cost-value reconciliations and financial forecasts gave the business a current view of revenue, cost and the anticipated result. Risk and opportunity formed part of that reporting, allowing commercial advice to be considered alongside the operational position.

The volume of change made that discipline particularly important. Each event was part of the emerging account, with its status followed through the project rather than left to be reconstructed from a collection of unresolved applications at the end.

As completion approached, the commercial records and outstanding matters could therefore be considered within an established process. The work performed during delivery provided the foundation for closing the account, rather than requiring the parties to start a new exercise once the site work had finished.

Outcome

The final account with the main contractor was agreed on the date of practical completion. The established project record reports that the client achieved its expected return and gained financial certainty despite the substantial volume of change.

Our contribution was to maintain a consistent commercial thread from the replacement appointment through delivery and close-out, enabling the final-account discussion to reach a conclusion alongside completion of the works.

Back to projects