Delay and storage claim for a façade subcontractor
- Client
- Specialist façade subcontractor
- Service
- Claims
- Location
- United States
- Value
- Approximately US$19 million subcontract value
- Sector
- Commercial construction
We supported an international façade subcontractor preparing a claim for additional time, prolongation and off-site storage costs on a commercial project in the United States. Our work connected the independent delay analysis with recorded resources, agreed rates and storage evidence, while addressing a substantial counterclaim.
Background
The façade works had finished almost ten months later than planned. An extension of time of 175 days had already been agreed, together with associated delay costs, but further time and cost remained unresolved. Extended material storage costs had been reserved for later assessment and remained outstanding.
The main contractor had also presented a counterclaim of around US$1.4 million, including allegations that late deliveries and materials stored on site had delayed other trades. The client needed a claim that explained its remaining entitlement and responded to those allegations to support final account discussions.
Our approach
We separated the work into the outstanding delay claim, extended storage and the counterclaim response. An independent delay expert compared planned and actual progress across five time windows, tracking the critical path of the façade package. The analysis considered structural readiness, installation constraints and the effect of resequencing work.
We aligned the valuation with that analysis and the time already agreed. The claim sought a further 107 days, beyond the earlier 175-day extension. We identified the remaining periods within the relevant delay events so that costs already covered by previous agreements were not claimed again.
For personnel, we used the hours recorded against the project during those periods and applied the hourly rates used in the agreed change orders as required by the contract. The valuation schedules showed the calculation by person, month and delay event, allowing the resources claimed to be traced back to the underlying records.
We reviewed accommodation, utilities and expenses separately. Monthly accommodation costs were converted into daily averages and applied to the relevant delay days. Non-time-related expenses were excluded, and the overhead and profit allowance followed the contract provisions.
Storage required its own assessment because it remained outstanding over a wider period than the additional 107 days. We reviewed the change-order history and the earlier reservation of storage costs. The monthly valuation used the number of crates held, their average footprint and the storage rate, with supporting evidence of the facility, handling and equipment costs behind that rate.
We also prepared an itemised response to the counterclaim. Delay allegations were considered alongside the independent programme analysis, while other backcharges were reviewed against the scope, correspondence and supporting records. This distinguished disputed responsibility from the separate question of how an amount had been calculated.
Outcome
We delivered a claim report with the independent delay analysis, detailed valuation schedules, recorded-hours extracts and storage substantiation. It set out a claim for 107 additional days and a gross amount of approximately US$0.9 million in delay and storage costs, together with a reasoned response to the contractor’s counterclaim.
The client subsequently secured the full additional time and costs claimed and successfully rebutted the contractor’s counterclaim.