Understanding manufacturing losses and overhead recovery
- Client
- Specialist manufacturer
- Service
- Claims
- Location
- United Kingdom
- Value
- Confidential
- Sector
- Nuclear supply chain
We supported a specialist manufacturer seeking to understand substantial cost under-recovery on a long-term nuclear infrastructure supply programme. A planned production transition had extended well beyond its original timetable. We brought together contract pricing, manufacturing progress, labour utilisation and payment recovery to establish where the shortfalls arose and give the client a structured financial position.
Background
The manufacturer had committed capacity for a production phase expected to last around a year. As the programme extended, factory overhead continued while the output through which those costs were recovered fell behind the original plan.
An earlier production phase was also continuing alongside the later work. The two phases recovered overhead differently: one through certified process hours, the other through component prices. Understanding the financial exposure required the pricing, manufacturing and payment information to be read together. Contractual responsibility for individual delays was considered in a separate strand of the wider commission.
Our approach
We went back to the pricing schedules to establish how the contract was intended to recover overhead, processing costs and earlier investment. This involved distinguishing the allowances within component prices from amounts recovered through labour hours and other payment mechanisms.
We compared the baseline and revised production programmes at component level. The analysis translated overhead allowances into daily and monthly amounts, then related them to the movement in manufacturing and completion dates. Defined cut-off dates kept the historical assessment separate from costs that would continue to arise.
Payment applications and certified process-hour records were used to identify recovery already achieved through the overlapping phases. We credited those amounts within the financial model and deducted sums covered by earlier variations. This was important because the same factory resources could support more than one part of the programme, while their cost recovery appeared in different records.
Labour utilisation required a separate review. We examined monthly productive and indirect hours, the basis of the pricing assumptions and the treatment of recorded non-productive time. The supporting review addressed breaks, supervision and unusual shift entries, and distinguished work manufactured in the factory from bought-in components. This made the assumptions behind the utilisation calculation visible for review.
We also examined the effect of inflation on unrecovered overhead and on earlier investment costs built into future component prices. Delayed production affected when those amounts would be recovered. The calculations therefore distinguished the original pricing allowances, their escalation assumptions and the effect of the extended recovery period. Financing effects were identified separately from the underlying cost recovery, with their basis made explicit.
The report and supporting schedules brought these calculations into one financial view, with the component, period and calculation basis retained. We continued updating the model as production and payment information changed, keeping previous recoveries and outstanding exposure visible.
Outcome
One issued assessment set out financial losses at a defined historical cut-off, supported by a report and detailed calculations. This was a quantified financial position before determining which elements were contractually recoverable, and the model continued to develop as the programme progressed.
The client had a clearer account of where its financial exposure arose, how the costs had been calculated and what had already been recovered. That provided the financial foundation for the separate event-based recovery work, with the assumptions and adjustments available for examination during commercial discussions.