Commercial support for a river channel subcontract


Client
Civil engineering subcontractor
Service
Project Quantity Surveying
Location
United Kingdom
Value
Approx. £360,000 subcontract
Sector
Water and civil engineering

We supported a civil engineering subcontractor on a river channel repair project with a subcontract value of approximately £360,000. Additional work, temporary works difficulties and repeated programme rejections had put the commercial relationship under strain. We brought the events, evidence and valuations into a structured position for the main contractor to assess.

Background

The work involved concrete repairs within a river channel, with temporary arrangements needed to manage water around the workface. Conditions encountered on site led to additional repair requirements, while changes to the temporary dam and flume arrangements affected the sequence and ability to work.

The subcontractor was seeking additional time and cost while exposed to delay damages. Programme submissions were being rejected, and the parties disagreed over aspects of the instructions, temporary works and notified events. Those issues needed to be examined together because the programme position affected the commercial assessment.

Our approach

We began with the client’s operational and commercial teams to establish the history and identify the issues requiring action. We reviewed the subcontract, instructions, early warnings and compensation event records, separating the additional permanent works from temporary works matters and questions about responsibility.

The temporary works review considered the design information available at tender, the flow information provided and subsequent changes to the flume arrangement. We also examined the requirements for later phases. This allowed the team to distinguish its existing design responsibilities from matters that needed clarification or a separate commercial response.

We brought instructions, early warnings and compensation events into a working tracker. For each event, this recorded its description, submission history, proposed value, agreed position, programme adjustment and the parties’ comments. Agreed amounts and durations could be identified alongside matters still requiring substantiation or a decision.

The additional repair work required detailed scope checks. The records included defects identified on drawings but absent from the pricing schedule, further cracking found during the works and changes in repair requirements. We linked the relevant instructions and site information to the quantities and resources required, so that the quotations explained the work being valued.

We reviewed the cost build-ups for labour, materials, plant and time-related preliminaries against the subcontract valuation arrangements. The event schedules also made clear where direct work had been priced but the associated preliminaries or programme effect remained to be addressed. That distinction helped prevent an apparent agreement on one element from obscuring the outstanding position.

Programme acceptance was a separate priority. The client introduced a planning consultant to assist with the impacted programmes, and we worked alongside that input to connect the programme position with the notified events and commercial submissions. The aim was to present the time effect and its supporting records in a form the contractor could assess.

We continued supporting early warning and compensation event submissions, quotations and monthly valuations. Regular reviews with the client’s team kept the tracker and action plan current as the next phase approached, including identifying items to carry into the next application rather than leaving agreed work unclaimed.

Outcome

The work supported agreement of additional cost and an extension of time for the relevant compensation event, addressing the associated exposure to delay damages. The retained tracker records agreed event durations and values as well as items requiring further action.

The client had a clearer record of its commercial position and a practical basis for continuing the remaining work. Instructions, supporting information, programme effects and valuation status could be followed together, helping its teams manage the account through the continuing changes.