Substantiating the time and cost effects of late access
- Client
- MEP contractor
- Service
- Claims
- Location
- United Kingdom
- Value
- Approx. £13m subcontract
- Sector
- Residential development
We supported an MEP contractor dealing with late access to a residential development under an approximately £13 million subcontract. The account involved about 25 weeks of delay and a loss-and-expense claim of approximately £530,000. We pursued immediate commercial progress alongside a detailed reconstruction of access dates, design information and the time-related costs being advanced.
Background
The contractor had mobilised following its instruction to commence, but the apartments were not released in line with the agreed sequence. Access varied between blocks, and the developing architectural information also affected the contractor’s ability to complete its design obligations.
Commercial dialogue had not resolved the consequences. The client needed a substantiated time-and-cost position while also seeking opportunities to improve the account in the shorter term.
Our approach
We worked with the client on two connected tracks. The first focused on areas of the account where an improvement in certification could be progressed. The established client record reports an initial cash improvement of approximately £120,000 and an acknowledgment that the late-access issue required compensation.
The second track reconstructed the basis of the claim. Workshops with the technical, operational, planning and commercial team established the relevant history and the information needed to demonstrate the effects of the delayed access.
We compared the contractual and programme access dates with recorded apartment-release information. The assessment distinguished the dates for the separate blocks and identified the block driving the overall completion sequence, rather than simply adding together every late start.
The claim sought an overall completion adjustment of about 25 weeks, while the loss-and-expense assessment addressed a compensable period of approximately 23 weeks. Keeping those periods distinct helped explain why the time application and cost calculation did not use an identical duration.
We also examined the development of the architectural and construction information, comparing contract drawings, later revisions and the contractor’s design obligations. This connected the access account with the information needed to perform the installation work.
For prolongation, we worked through the finance-system records and checked the supporting invoices and timesheets. The assessment distinguished the date a transaction appeared in the accounting system from the period to which the cost related, using the relevant transaction information to allocate it to the claimed period.
The cost review excluded fixed costs, entries outside that period and items unsuitable for the prolongation assessment. Staff allocation and changes to time-recording arrangements were examined alongside site expenses, design resources and supply-chain costs. Inflation and overhead components were then identified separately.
The resulting report linked the contractual basis, access evidence, time calculation and cost schedules. It gave the client a document suitable for further commercial discussions and a foundation for formal proceedings if those discussions did not progress.
Outcome
The client achieved the initial commercial improvement described in the established case-study record and received a detailed claim report supporting the further time-and-cost position. The work provided a platform for negotiating the final account.
Our contribution was to combine immediate account progress with a traceable explanation of the delay and its financial effects, giving the client a clearer basis for the next stage.