Independent quantum assessment of additional fire protection costs
- Client
- Main contractor
- Service
- Expert Witness
- Location
- United Kingdom
- Value
- Confidential
- Sector
- Retail and leisure
We supported a main contractor and its solicitors with independent quantum expert evidence for an adjudication concerning additional fire protection works on a retail and leisure development. The claim arose from alleged omissions in the original design. We examined the work undertaken, the subcontract records and the costs incurred to provide a reasoned valuation of the claimed losses.
Background
Additional fire barriers and protection around structural steelwork had been installed during construction. The contractor sought to recover the resulting costs from its designer, relying on a specialist fire protection subcontractor’s application as the basis of its claim.
The quantum review needed to establish what the records supported, including the quantities, agreed rates and costs the contractor had incurred. Architectural expert evidence addressed the alleged design failures separately. Our valuation proceeded on the stated assumption that liability would be established.
Our approach
We organised the claim into five principal items and traced each back to the relevant design information, instructions and subcontract records. We requested further drawings, quotations, payment information, installation records and photographs, maintaining a document register so that the basis of the opinion could be followed.
For the principal wall-head barrier, we compared the tender detail with the later construction drawings to understand the additional work claimed. We then remeasured approximately 600 metres of barrier from the drawings and prepared annotated measurement sheets. This included checking both sides of compartment walls, changes in roof pitch and whether details shown on the drawings had actually been constructed.
The installed work also had to be checked against the quantities claimed. In one area, changes to the unit layout meant a wall shown on the design was not built. We examined this difference rather than assuming that every drawn detail represented an incurred cost. Photographs were also considered alongside the drawings when reviewing claims for wider or additional barriers.
For the steelwork protection, we checked more than 300 bracing locations and several dozen beam locations. Monthly seal registers recorded installation locations, sizes, quantities and rates. We compared these with the specialist’s dated job sheets and installation photographs, then checked the rates against the quotations and agreements made before the work.
We reconciled the claimed amounts with payment certificates and the subcontractor’s acceptance of its final account. This distinguished the submitted application from the contractor’s actual cost liability. Where a remeasurement or a quoted rate was higher than the cost incurred, we retained the incurred amount. Access-equipment costs were checked separately against the quoted and certified sums.
We also considered the procurement circumstances. The specialist was already working on the project, and the contractor’s witness evidence explained the urgency of completing the additional protection and the programme consequences of a separate tender exercise. That evidence informed our opinion on the reasonableness of using the existing specialist.
The report set out an assessment for each item, with reasons for differences from the claim and references to the supporting records. Amounts without sufficient evidence of the work undertaken or its connection to the alleged design omission were excluded from the valuation.
Outcome
We delivered an independent expert report and supporting valuation assessing the losses on the report’s stated assumptions. The package included annotated measurement drawings and the document register, making the quantities, rates and adjustments available for examination.
The contractor and its solicitors had a clear financial assessment for the adjudication, with the basis of each amount explained. The work established the quantum opinion independently of the separate questions of design responsibility and liability. Quantum was not considered in the adjudication. The valuation remained our independent expert opinion, rather than an adjudicator’s award or money recovered.