Project quantity surveying for an NEC decarbonisation scheme
- Client
- Regeneration contractor
- Service
- Project Quantity Surveying
- Location
- United Kingdom
- Value
- Approx. £1.1m contract
- Sector
- Public sector decarbonisation
We supported a regeneration contractor delivering a public-building decarbonisation scheme under NEC3 Option A. The approximately £1.1 million contract combined mechanical and electrical upgrades with associated building works over an 18-week construction period. We managed the commercial work from commencement through to final account, giving the project team a consistent view of payments, change, cost and risk.
Background
The scheme brought together new heating plant, electrical infrastructure and building work within an existing public facility. Its activity-schedule contract required the commercial team to connect progress on site with payment assessments while managing changes and unresolved allowances through the agreed contractual processes.
The contractor also needed reliable monthly reporting. Package expenditure, consultant costs, preliminaries, contingency and changes all contributed to the project forecast. Keeping those elements visible was important to protecting the commercial position during a relatively short delivery period.
Our approach
We reviewed the main contract and set out its commercial requirements, including the payment arrangements and the process for managing change. This gave the site and contracts managers a reference for their obligations and helped align the main contract administration with the subcontract packages.
On the supply chain side, we assessed monthly applications, prepared and issued payment notices, and reviewed compensation events. We worked within the client’s financial system where required, keeping the commercial administration connected to its internal controls and reporting.
Main contract applications and the change account were managed alongside that subcontract work. Our payment tracker brought the submission, assessment, certification, invoicing and payment dates into one record, with fields for notices and follow-up. This helped the team distinguish an amount applied for from the amount certified and the further steps needed to obtain payment.
We also maintained a structured compensation-event record. It identified quotation and response dates, the project manager’s decision and the instructed amount, alongside the follow-up process if a response or assessment was outstanding. For example, the retained record shows a pipework-related change progressing from quotation to acceptance rather than remaining an unresolved adjustment at the end of the project.
The monthly reconciliation separated value and cost across the main building package, heating plant, electrical connection, consultant input, contractor preliminaries and other project allowances. The cash-flow profile placed that information against the delivery period, giving the client a clearer view of the forecast and its timing.
Provisional sums and risk matters were addressed through the commercial and risk meetings. We kept the treatment of unresolved scope visible within the wider account and supported the team as the detail developed. The focus was on dealing with issues during delivery and carrying a traceable record into the final account.
We led the final account agreement, bringing the payment and change position together so that the commercial close-out followed the work already undertaken throughout the project.
Outcome
The project delivered the client’s planned margin, with final account matters resolved at practical completion. The existing case record also reports completion to time and budget, without a contractor claim being left for the council to resolve.
The approach provided a commercial model for the client’s further programme of decarbonisation schemes. Its value was a consistent service through the whole commission: regular reporting, timely administration and a clear route from the original activity schedule to the agreed account.