Market testing and pricing support for an education construction framework
- Client
- Main contractor
- Service
- Tendering
- Location
- Four English regions
- Value
- Confidential
- Sector
- Education
We supported a main contractor preparing a bid for a Department for Education construction framework. Our role was to develop market evidence for external works and abnormal costs across six trade packages and four regions, giving the client’s estimating team a structured basis for its framework pricing decisions.
Background
The client needed pricing evidence for a harmonised rate book covering future school projects. The tender timetable was tight, internal resources were limited and the design information was less developed than it would be for an individual construction contract.
Securing useful supply chain engagement also required a clear enquiry. This was a framework pricing exercise rather than an immediate project award, and the prices needed to be understood alongside their assumptions, regional coverage and commercial qualifications. Groundworks returns involved sums running into several million pounds, making differences in scope and preliminaries significant to the bid.
Our approach
We developed a package enquiry and analysis strategy for groundworks, piling, fencing, soft landscaping, sports equipment and street furniture. Our work complemented the client’s base-build estimating and fed into its framework rate book and final pricing checks.
We used information from two reference school schemes to give suppliers a defined basis for their returns. The comparisons distinguished primary and special educational needs provision from secondary school requirements and supported enquiries across the North West, East Midlands, London and South West.
For groundworks, we set out a standard site baseline covering matters such as ground conditions, access and obstructions. We separately sought information on the effect of abnormal conditions, including restricted access, contamination, sloping sites and work during term time. This made the basis of the rates explicit and identified where additional allowances might be needed.
The enquiry packs brought together the relevant drawings, pricing schedules and assumptions. We coordinated clarifications with the client and recorded what each return included. This was particularly important where suppliers priced different scopes or attached conditions to their offer.
We assembled comparisons aligned to the rate book sections and examined the treatment of preliminaries, mobilisation and specialist requirements. Some prices included allowances that others excluded. We made these differences visible, alongside unpriced items and provisional rates used for comparison, so the client could distinguish supplier quotations from assumptions requiring further review.
We also checked interfaces between packages. A specialist green-screen fencing item required input from the landscaping supply chain. Street furniture quotations needed to be read alongside installation requirements, while piling returns contained qualifications on working platforms, testing and spoil removal. These details mattered because a headline rate could leave an associated activity to be priced elsewhere.
The package summaries brought the commercial information together: regional availability, price validity, lead times, attendances, exclusions and the basis of the figures being compared. The workbooks and commentary enabled the client to review the market evidence in a consistent format and carry the relevant qualifications into its own pricing decisions.
Outcome
We provided comparison workbooks and supporting summaries for the six packages, with regional rates, preliminaries and pricing qualifications made visible. This gave the client a documented basis for reviewing its external works and abnormal-cost allowances, supported by market returns and a clear record of the assumptions behind them.
The client highlighted our “responsiveness, professionalism, and clear communication” in its feedback. Our contribution supplied the pricing evidence and analysis its team needed alongside its wider bid strategy and framework submission.