Maintaining commercial control on a challenging MEP subcontract
- Client
- MEP specialist
- Service
- Project Quantity Surveying
- Location
- United Kingdom
- Value
- Approx. £7m subcontract
- Sector
- Energy from waste
We supported an MEP specialist providing works under a bespoke subcontract worth approximately £7 million on an energy-from-waste project. With financial performance under pressure and short contractual notice periods, the team needed dependable contract administration, a current forecast and a clear record of change. We provided quantity surveying support across the main account and the supply chain.
Background
The project combined mechanical and electrical installations across several process and support areas. Access, sequencing and the readiness of workfaces could affect the method of installation as well as the resources needed to carry it out.
The client needed an objective view of its financial position while maintaining the records and notifications required by its subcontract. The commercial function also had to deal with applications, variations and delay claims from its own subcontractors.
Our approach
We reviewed the bespoke agreement and translated its obligations into working processes and templates. Particular attention was given to the short notice periods, so that the site and commercial teams had a practical route for raising issues requiring a contractual response.
The change records distinguished the event from its price and any separate time effect. One example concerned a change from powered access platforms to smaller towers and other access equipment. The quotation identified the additional labour needed to erect and move that equipment, the access hire and the effect of the changed method on installation efficiency.
That submission expressly separated the additional working-method cost from any extension-of-time cost. Keeping those elements distinct helped the team explain what was included in the quotation and what remained to be addressed elsewhere in the account.
We maintained financial reporting alongside that contract administration. The cost-value reconciliation separated costs booked to date from costs still forecast, with materials, subcontractors, management resources and site expenses identified within the underlying schedules. Movements between reviews could therefore be traced to the cost heading driving them.
The revenue assessment also distinguished the original subcontract value from variations and the reserve held against them. This allowed management to understand the forecast without treating every amount put forward as certain recovery. Cash-flow forecasts and monthly reports complemented the applications for payment and forecast final account issued upstream.
Within the supply chain, we reviewed payment applications, variations and delay claims with the project team. The work connected the subcontract terms with the supporting records and valuation, helping the client decide what should be assessed, queried or progressed towards agreement.
Close working relationships were central to keeping that information current. Regular communication with the delivery team brought emerging constraints into the commercial process and allowed the reports to reflect the issues being encountered on site.
Outcome
The client had a clearer view of forecast performance and the actions needed across both its main account and subcontract accounts. The established case-study record also reports the satisfactory resolution of a number of supply-chain delay claims.
Our contribution was to maintain an organised commercial position on a financially difficult project, giving business leaders the information needed to assess exposure and make informed interventions.