Extension of time and cost claims for a major logistics project


Client
Specialist MEP subcontractor
Service
Claims
Location
United Kingdom
Value
Approx. £12m subcontract
Sector
Logistics and distribution

We supported a specialist mechanical and electrical subcontractor on a logistics development with a subcontract value of approximately £12 million. Late and fragmented access had disrupted installation across several sections, while contractual completion dates exposed the business to substantial delay damages. We brought the contract history, programme evidence and cost records together to prepare a detailed claim and inform the client’s negotiating strategy.

Background

The subcontract covered a large distribution building, offices and associated external works. Different sections had their own completion obligations, and the installation depended on other trades releasing work areas in the required condition. Some access was provided in stages, with parts of the building also made available to the employer before the subcontract works were complete.

By the time the first phase reached practical completion, it had overrun by approximately 11 months. The client had received no corresponding agreement of its time and cost position. Earlier forecasts included substantial prolongation and acceleration costs that the main contractor had assessed at nil, alongside potential damages exposure of more than £5 million. The business needed a realistic assessment of its position and a documented route to recovery.

Our approach

We first reconstructed how the programme obligations had been agreed. Pre-contract minutes, letters of intent, notices to commence, programme revisions and the eventual subcontract amendments did not present a straightforward chronology. We worked with the client’s project, commercial, planning and legal teams to distinguish the original installation sequence from the dates ultimately incorporated into the contract.

The access claim was developed around 11 events. For each area, we established when access was required, what preceding work remained outstanding, and when the workface became available in the condition assumed by the programme. Progress reports, correspondence, photographs and site records substantiated the difference between limited access and access that allowed the intended sequence to proceed.

Working with the client’s planners, we connected those events to the affected activities and sectional completion dates. The review also tested the limitations of the available programmes, including missing logic and gaps in progress updates. This informed both the delay assessment and the advice given to the client about the strength of its evidence.

The cost work separated prolongation from reduced productivity and acceleration. Monthly actual costs were filtered and organised into relevant heads, then weighted to the access-event periods to derive daily prolongation rates. Preliminaries already recovered through variations were credited. The resulting calculation distinguished a longer span of access disruption from the assessed extension to completion.

For productivity, actual labour hours were compared with earned hours from the progressed programme, including variation resources. The separate acceleration submission examined timesheets, payroll records, daywork sheets and subcontractor payments. It identified the additional overtime premium above the basic labour cost and apportioned costs between phases, rather than claiming all overtime expenditure as an acceleration loss.

We presented the findings and evidential limitations to the client’s leadership. That review supported decisions about financial reporting, further substantiation and the scope of the material to be put to the main contractor.

Outcome

The submitted access-delay claim sought approximately £1.8 million and extensions of time of up to approximately seven months across the affected sections. It set out the contractual basis, event narratives, programme effects and valuation with supporting particulars. Acceleration and other reserved matters were kept separate so that the scope of this submission was clear.

The client had a substantiated position for commercial discussions and a clearer understanding of both its recovery arguments and remaining exposure. Our contribution was to turn a disputed project history into an organised basis for negotiation, supported by detailed analysis and objective advice.